Construction Update - week of June 30, 2014



Construction Update - week of June 30, 2014

Butler Center Expansion/Fontbonne Hall Renovation

Construction Update – June 30, 2014

Last week:

  • Fontbonne wall construction continues. Wallboard sheeting has begun up high.
  • Sidewalk on the south sides of Butler and Music were both poured.
  • The old electrical wiring was removed from the area of the three-story addition.
  • Storm and sanitary sewer routes are being prepared.
  • The demolition inside the Butler Center front entry was almost completed.

Safety – No incidents or accidents to report.

This week:

  • Re-routing the construction perimeter in order to open up the south entry of the Music Building.
  • Beginning to construct the exterior walls of the new stairwell in Butler.
  • Mechanical and Electrical contractors will continue in Fontbonne. Foundation footings will continue for the 3-story construction.

Next week:

  • Fontbonne windows should begin arriving.
  • Foundation walls will begin for the 3-story construction.
  • Fontbonne classroom walls will begin being sheetrocked and room sizes will become more visibly evident.