Construction Update - week of July 14, 2014

Butler Center Expansion/Fontbonne Hall Renovation

Construction Update – July 14, 2014

Last week:

  • Fontbonne wall construction continues. Wallboard sheeting has begun up high.
  • Soil corrections are completed in the three-story footprint
  • Storm sewer piping was 60% replaced.
  • Footings have been set and poured for the Butler Center front entry
  • Electrical, Mechanical, Plumbing, and Sprinkler crews continue their progress in getting Fontbonne ready.

Safety – No incidents or accidents to report.

This week:

  • Steel begins to arrive for the Butler Center front entry.
  • Fontbonne windows are beginning to be installed.
  • Window and door frames (interior) will be delivered and installation will start.
  • Foundation footings continue for the 3-story construction.

Next week:

  • Fontbonne windows will continue being installed.
  • Foundation walls continue for the 3-story construction.
  • Drywall on the Fontbonne walls will near completion.
  • Footings for the Fontbonne elevator will be poured.  Rain delayed this start.