Construction Update - week of August 4, 2014



Construction Update - week of August 4, 2014

Butler Center Expansion/Fontbonne Hall Renovation

Construction Update – August 4, 2014

Last week:

  • All Fontbonne window frames are in (glass is not complete yet)
  • Footings for the Training Center began
  • Footings for the Fontbonne elevator began
  • Steel assembly for the Butler Center front entry and roof continued
  • Most sheetrock in Fontbonne was installed, taping and painting began
  • Floor tile was installed in the main floor of Butler

Safety – No incidents or accidents to report.

This week:

  • Training center footings continue
  • Water line bypass piping is being installed for underground water supply
  • Butler front entry stairs and framework should arrive
  • Structural interior walls of the three-story are being built

Next week:

  • Tip-up walls will start going up on the three story
  • Carpet could begin in Fontbonne
  • Ceilings and lighting will begin installation in Fontbonne
  • Fontbonne elevator walls will begin being constructed.