Construction Update – week June 25, 2014

Loginlocked

 

Construction Update – week June 25, 2014

Butler Center Expansion/Fontbonne Hall Renovation

Construction Update – June 25, 2014

Last week:

  • Fontbonne wall construction continues.
  • Work on the three-story footings is started.
  • The power switch-over to the new transformer is completed.
  • The floor tile has been removed in Butler Center 1st  & 2nd floor.

Safety – No incidents or accidents to report.

This week:

  • Pouring sidewalk and ramping for the coaches entrance to Butler and the south entrance to the Music Building.
  • Foundation work will begin for the new stairwell in Butler.
  • Main power connections/changes will be accomplished.
  • Foundation footings will continue for the 3-story construction.
  • Electric and Plumbing crews will work in Fontbonne with the framers putting up stud walls.

Next week:

  • Wall construction begins for the Butler south stairwell.
  • Foundation footings will continue for the 3-story construction.
  • Fontbonne classroom walls will continue with electrical installations and sheetrock.